2017-2018

Refurbishment of the public swimming pool Reinach

The public swimming pool in Reinach was built in the 1950’s in a unique environment and was in need of structural and technical refurbishment. Our company was called in to manage the final construction phase from January to June 2018 with Morger Partner. The goal was to bring the technically and architecturally demanding project to a solid and good ending. The entire pool engineering and technical components were put underground. The renovation of the actual pools had to be scheduled simultaneously with the renovation of the surrounding buildings, the biggest challenge being the coordination of planners, specialists and contractors in view of the opening date. We are proud to say that the pools were opened on schedule on June 16th 2018.

Building contractor:

Gemeinde Reinach, BL

Architect and general planner:

Morger Partner, Basel

Employer:

Morger Partner, Basel

Construction management final phase:

Bernstein Bâtir AG, Basel

Realisation:

2017-2018